AIP Supplement for Malaysia

AIRAC AIP SUP

48/26

Effective Date: 26 NOV 2026

Publication Date: 15 OCT 2026

  PENANG INTERNATIONAL AIRPORT (WMKP)
UPGRADING AND EXPANSION OF PENANG INTERNATIONAL AIRPORT, AIRSIDE FACILITIES - PAVEMENT WORKS AND OTHER ASSOCIATED WORKS, WORK SCHEDULE AND MOVEMENT AREAS RESTRICTIONS

1  INTRODUCTION

1.1  The Penang International Airport is currently undergoing an upgrade program. This involves the expansion of the main apron, rehabilitation of the existing apron taxiway, introduction of a new helicopter apron, and introduction of a New Aircraft Stand Taxilane L, new helicopter Stand Taxilane M and New Aircraft Stand Taxilane N.

1.2  The following temporary changes concerning Penang Aerodrome (WMKP) is taking place due to upgrading works from 1st March 2025 until 1st July 2027.This project is structured into four distinct phases. A comprehensive breakdown of the specifics for each phase can be found in the table provided below:

PhaseStart DateFinish Date
1Phase 3 (Apron Taxiway Rehabilitation Works)19th JUL 202622nd JUN 2027
2Phase 4 (Realignment Apron Taxiway)23rd JUN 20271st JUL 2027

1.3  The working areas for the rehabilitation exercise are detailed in the remarks.

  1. APRONS, TAXIWAYS AND CHECK LOCATIONS / POSITIONS DATA

    Apron surface and strengthBay 1L, Bay 1, Bay 1R, Bay 2, Bay 3, Bay 5, Bay 8, Bay 11
    Surface: Concrete (Rigid)
    Strength: PCR 1360 / R / D / W / U
     Bay 4, Bay 5L, Bay 5R, Bay 6, Bay 7, Bay 8L, Bay 8R
    Surface: Concrete (Rigid)
    Strength: PCR 685 / R / C / W / U
     Bay 3R, Bay 9, Bay 10, Bay 11L, Bay 11R
    Surface: Concrete (Rigid)
    Strength: PCR 704 / R / D / W / U
     Bay 3L, Bay 2L, Bay 2R
    Surface: Concrete (Rigid)
    Strength: PCR 157 / R / D / W / U
     Bay A1, Bay A2, Bay A3, Bay A4, Bay A5, Bay A6
    Surface: Concrete (Rigid)
    Strength: PCR 1250 / R / C / W / T
     Bay H1, Bay A7
    Surface: Concrete (Rigid)
    Strength: PCR 160 / R / C / W / T
     Bay 12, Bay 12L, Bay 12R, Bay 13, Bay 14, Bay 15L, Bay 15, Bay 15R, Bay 16, Bay 16R, Bay 17, Bay 18, Bay 19
    Surface: Concrete (Rigid)
    Strength: PCR 1250 / R / C / W / T
     Bay C1
    Surface: Concrete (Rigid)
    Strength: PCR 800 / R / C / W / U
     Bay C2 and Bay C3
    Surface: Concrete (Rigid)
    Strength: PCR 715 / R / B / W / U
    Taxiway width, surface and strengthTaxiway A and Taxiway E
    Width: 23 m
    Surface: Asphalt (Flexible)
    Strength: PCR 577 / F / A / W / U
     Taxiway A/04
    Width: 30 m
    Surface: Concrete (Rigid) and Asphalt (Flexible)
    Strength: PCR 787 / R / A / W / U and PCR 577 / F / A / W / U
     Taxiway A/22
    Width: 30 m
    Surface: Asphalt (Flexible)
    Strength: PCR 577 / F / A / W / U
     Taxiway B
    Width: 34 m
    Surface: Concrete (Rigid) and Asphalt (Flexible)
    Strength: PCR 643 / R / A / W / U and PCR 481 / F / A / W / U
     Taxiway C
    Width: 23 m
    Surface: Asphalt (Flexible)
    Strength: PCR 481 / F / A / W / U
     Taxiway D
    Width: 34 m
    Surface: Asphalt (Flexible)
    Strength: PCR 481 / F / A / W / U
     Taxiway FWidth: 31 mSurface: Asphalt (Flexible)
    Strength: PCR 577 / F / A / W / U
     Taxiway GWidth: 32 mSurface: Asphalt (Flexible)
    Strength: PCR 577 / F / A / W / U
     Taxiway HWidth: 42 mSurface: Concrete (Rigid) Strength: PCR 1250 / R / C / W / T
     Taxiway JWidth: 25 mSurface: Concrete (Rigid)
    Strength: PCR 715 / R / B / W / U
     Aircraft Stand Taxilane J1Width: 25 mSurface: Concrete (Rigid)
    Strength: PCR 715 / R / B / W / U
     Apron Taxiway KWidth: 24 mSurface: Concrete (Rigid) Strength: PCR 1250 / R / C / W / T
     New Aircraft Stand Taxilane LWidth: 24 mSurface: Concrete (Rigid) Strength: PCR 1250 / R / C / W / T
     New Helicopter Stand Taxilane MWidth: 13 mSurface: Concrete (Rigid) Strength: PCR 160 / R / C / W / T
     New Aircraft Stand Taxilane NWidth: 20 mSurface: Concrete (Rigid)Strength: PCR 160 / R / C / W / T
    RemarksPHASE 3 (APRON TAXIWAY REHABILITATION WORKS)Several amendments and changes to the Aircraft Operations Area (AOA) will take place during this phase. The changes and amendments affecting the AOA are listed below in the order shown:
     
    1. Activation of new Helicopter Bay H1.

    2. Activation of Temporary Bay T3.

    3. Activation of new Helicopter Stand Taxilane M.

    4. Activation of new Aircraft Stand Taxilane N.

    5. Temporary closure of apron bays B5 and B7.

    6. Temporary closure of apron bays A5, A4L and A4.

    7. Temporary closure of apron bays A4R, A4 and A3.

    8. Temporary closure of TWY G.

    9. Temporary closure of apron bays A2, A1L, A1R, A1, B1 and B3.

    10. Temporary closure of apron bays A6L, A6, A6R, A7L, A7, A7R, A1 and A8.

    11. Temporary closure of TWY F.

    12. The Centreline of apron TWY K shall be shifted forward by a distance of 26 m in phases for the apron TWY K rehabilitation works (Refer to APPENDIX 1B).

    13. Apron TWY K, starting from TWY F up to TWY G, will be used for Code C aircraft (wing span not more than 36 m) throughout the construction period from the commencement.

    14. Temporary Closure Bay A4, A1 and B7, while the apron TWY K rehabilitation works are being carried out.

    15. Temporary Closure Bay 19 to facilitate the movement of GSE and AFRS vehicles throughout the Work In Progress (W.I.P) until the project is completed.

     Note: The effective dates of all operational changes associated with Phase 3, including the introduction of new facilities and temporary closures, will be promulgated by NOTAM and/or AIP Amendment (AIP AMDT), as appropriate, in accordance with the AIRAC cycle where applicable.
     PHASE 4 (APRON TAXIWAY REALIGNMENT)Several amendments and changes to the Aircraft Operations Area (AOA) will take place during this phase. The changes and amendments affecting the AOA are listed below in the order shown:
     
    1. Re-configuration of existing aircraft bays A5, A4L, A4, A4R, A3, A2, A1L, A1, A1R, B1, B3, B5, B7, A6L, A6, A6R, A7L, A7, A7R, A1 and A8 into new aircraft bays 1R, 2L, 2, 2R, 3L, 3, 3R, 4, 5L, 5, 5R, 6, 7, 8L, 8, 8R, 9, 10, 11L, 11, 11R, 12L, 12, 12R, 13, 14, A1, A2, A3, A4, A5 and A6. (Refer to APPENDIX 2B).

    2. Activation of new Aircraft Bay A7 adjacent to Helicopter Apron Bay H1.

    3. Relocation of the existing Apron TWY K centreline to a new location.

    Note: The effective dates of all operational changes associated with Phase 4, including the introduction of new facilities and temporary closures, will be promulgated by NOTAM and/or AIP Amendment (AIP AMDT), as appropriate, in accordance with the AIRAC cycle where applicable.

  2. SURFACE MOVEMENT GUIDANCE AND CONTROL SYSTEM AND MARKINGS

    Remarks
    1. Taxiway lights not available for:

      1. Taxiway F effective from the date of temporary closure until the end of the taxiway closure period.

      2. Taxiway G effective from the date of temporary closure until the end of the taxiway closure period.

    2. Visual docking and guidance system will be permanently removed for:

      1. Bay A5, A4L, A4, A4R, A4, A3, A2, A1L, A1R, A1, B1, B3, B5, B7, A6L, A6 and A6R

    3. New visual docking and guidance system for:

      1. Bay 15L, 15, 15R, 16, 16R, 17, 18, 19, 11L, 11, 11R, 4, 5L, 5R, 5, 6, 7, 8L, 8, 8R, 9, 10, 12L, 12, 12R, 3L, 3, 3R, 13 and 14.

    Note: The effective date for each change and amendment to the Taxiway lights and Visual Docking and Guidance System will be notified from time to time via NOTAM or AIP Amendment, in accordance with the sequence of works.

  3. AERODROME OBSTACLES

    OBST ID /DesignationOBSTTypeOBST
    Position
    ELEV/
    HGT
    Markings/ Type,
    Colour
    Remarks
    PC-5Piling Crane051742.61N
    1001612.47E
    4 m / 19 mMarked/
    LIM R
    Piling machine reach 19 m.

    Obstacle in position effective from 6th May 2025 till 18th November 2026 EST.
  4. OTHER LIGHTING, SECONDARY POWER SUPPLY

    Remarks
    • Taxiway edge and centreline lights not available for:

      1. Taxiway F effective in Phase 3 (from the start date of the temporary closure until the end of the closure period).

      2. Taxiway G effective in Phase 3 (from the start date of the temporary closure until the end of the closure period).

    Note: The effective dates of all operational changes associated with Phase 3 & 4, including the introduction of new facilities and temporary closures, will be promulgated by NOTAM and/or AIP Amendment (AIP AMDT), as appropriate, in accordance with the AIRAC cycle where applicable.

1.4  Local traffic regulations (additional)

1.4.1  Taxiing to and from stands

  1. Aircraft movement will not be permitted in closed portions of the apron taxiway, parking bays and taxiways.

  2. The routes to be used by aircraft when taxiing entering or exiting from Apron will be specified by Air Traffic Control. The issuance by Air Traffic Control of a taxi route to an aircraft does not relieve the pilot-in-command of the responsibility to maintain separation with other aircraft on the movement area or to comply with Air Traffic Control directions intended to regulate aircraft movement.

  3. During the construction period, pilots are advised to be cautious of open excavation, workers, construction materials, and equipment, especially when taxiing on the Taxiway and Apron Taxiway near cordoned or barricaded areas where work is ongoing.

1.5  Parking Area For General Aviation Aircraft

1.5.1  Parking at the General Aviation (GA) Apron.

1.5.2  New Temporary Aircraft Bay T3 - Power in and Power Out mode (PIPO).

1.5.3  Temporary Bay T3 for General Aircraft with maximum wing span 27.05 m operating at GA Apron subject to allocation approval from Bay Allocation Unit MASB.

1.5.4  Opening of Bay H1 for helicopter parking with D-value 26 m and below.

2  CONSTRUCTION WORKING HOURS FOR RUNWAY, TAXIWAYS AND APRON TAXIWAYS

2.1  PHASE 3: APRON TAXIWAY REHABILITATION WORKS

2.1.1  Taxiway rehabilitation works will commence from existing Bay B7 to Bay A6L, and then continue from Bay A8 to Bay A7.

2.1.2  The taxiway closures will occur in phases, commencing with the closure of TWY G and subsequently followed by the closure of TWY F. Construction works on the shoulders of TWY F and TWY G outside the construction hoarding will be carried out during runway closure hours.

2.1.3  Apron marking will be carried out during runway closure hours.

2.2  PHASE 4: REALIGNMENT APRON TAXIWAY

2.2.1  All bay lead lines will be connected to the new apron taxiway centreline.

2.2.2  The centreline of the apron taxiway leading to all new aircraft bays will be realigned to match the new apron taxiway centreline.

2.2.3  Apron marking works will be carried out during runway closure hours.

3  CHARTS

3.1  Refer charts below for additional information:

  1. Apron Taxiway Rehabilitation (Phase 3)

    1. Appendix 1A: Aerodrome / Heliport Chart – ICAO (AD2-WMKP-2-1)

    2. Appendix 1B: Aircraft Parking Docking Chart – ICAO (AD2-WMKP-2-3)

    3. Appendix 1C: Aircraft Parking Docking Chart – ICAO (AD2-WMKP-2-4)

    4. Appendix 1D: Aerodrome Ground Movement Chart – ICAO (AD2-WMKP-2-5)

  2. Realignment Apron Taxiway (Phase 4)

    1. Appendix 2A: Aerodrome / Heliport Chart – ICAO (AD2-WMKP-2-1)

    2. Appendix 2B: Aircraft Parking Docking Chart – ICAO (AD2-WMKP-2-3)

    3. Appendix 2C: Aircraft Parking Docking Chart – ICAO (AD2-WMKP-2-4)

    4. Appendix 2D: Aerodrome Ground Movement Chart – ICAO (AD2-WMKP-2-5)

4  CONTACT

4.1  Any information and queries to contact:

Name:Mohd Ridzuan bin Ahmad Walid
Designated:Head of Operations, MASB Penang International Airport
Email:ridzuanaw@malaysiaairports.com.my

5  VALIDITY

5.1  This AIRAC AIP Supplement supersedes AIRAC AIP SUP 38/26 and will remain in force until the works complete on 1st July 2027 EST. Any updates, changes or cancellation to this supplement will be notified through NOTAM.

- END -

Figure 1. APPENDIX 1A
PDF../graphics/331277.pdf
Figure 2. APPENDIX 1B
PDF../graphics/331279.pdf
Figure 3. APPENDIX 1C
PDF../graphics/331280.pdf
Figure 4. APPENDIX 1D
PDF../graphics/331281.pdf
Figure 5. APPENDIX 2A
PDF../graphics/331284.pdf
Figure 6. APPENDIX 2B
PDF../graphics/331285.pdf
Figure 7. APPENDIX 2C
PDF../graphics/331288.pdf
Figure 8. APPENDIX 2D
PDF../graphics/331291.pdf